SolarEdge · SolarEdge SE3K–SE10K (three-phase inverter with power optimizers, SetApp) · Procedure
How to read an error and safely restart a SolarEdge three-phase inverter
Summary (editorial)
The error can be read in SetApp or from the LEDs. The manual describes the safe order for switching the inverter off and on.
✎ editorial – written from the cited sources, not a manufacturer statement. Status: draft.
From the manufacturer's documentation (English source wording, with page)
- Move ON/OFF/P switch to P for 2 seconds and release to show error type on LEDs[1]
- Red LED on bottom panel indicates an error; codes shown in SetApp and monitoring[2]
- LED table: arc / isolation-RCD / grid / high temperature / pairing / other[3]
- Switch OFF reduces optimizer voltage to safety voltage and inhibits export; control circuitry stays powered[4]
- After OFF wait until green LED blinks (DC < 50 V) or five minutes[5]
- Disconnect AC by turning OFF circuit breakers on distribution panel[6]
- Switch ON starts optimizers and power production[7]
- Cover may be opened only after switch OFF and 5 minutes wait[8]
⚠ Work on refrigerant circuits, mains electricity and PV DC wiring is for qualified technicians only.
The Polish page has more detail (plain-language explanation, safe checks, guides): Read in Polish →
Sources
Every statement has a footnote to the document and PDF page. “Quote verified” means the quote was found automatically in the text of that page.
- [1] Installation Guide – Three Phase System with SetApp Configuration, Europe (MAN-01-00505-1.8, 2024-10) (MAN-01-00505-1.8) , p. 51 official manufacturer document quote verified
Move the ON/OFF/P switch to P position for 2 seconds and release it
- [2] Installation Guide – Three Phase System with SetApp Configuration, Europe (MAN-01-00505-1.8, 2024-10) (MAN-01-00505-1.8) , p. 51 official manufacturer document quote verified
a red LED indicates an error
- [3] Installation Guide – Three Phase System with SetApp Configuration, Europe (MAN-01-00505-1.8, 2024-10) (MAN-01-00505-1.8) , p. 51 official manufacturer document quote verified
Isolation or RCD problem
- [4] Installation Guide – Three Phase System with SetApp Configuration, Europe (MAN-01-00505-1.8, 2024-10) (MAN-01-00505-1.8) , p. 22 official manufacturer document quote verified
OFF (0) - Turning this switch OFF
- [5] Installation Guide – Three Phase System with SetApp Configuration, Europe (MAN-01-00505-1.8, 2024-10) (MAN-01-00505-1.8) , p. 61 official manufacturer document quote verified
indicating that the DC voltage is safe (<50V)
- [6] Installation Guide – Three Phase System with SetApp Configuration, Europe (MAN-01-00505-1.8, 2024-10) (MAN-01-00505-1.8) , p. 43 official manufacturer document quote verified
Disconnect the AC to the inverter by turning OFF the circuit breakers on the distribution panel
- [7] Installation Guide – Three Phase System with SetApp Configuration, Europe (MAN-01-00505-1.8, 2024-10) (MAN-01-00505-1.8) , p. 22 official manufacturer document quote verified
Turning this switch ON (after power optimizer pairing) starts the
- [8] Installation Guide – Three Phase System with SetApp Configuration, Europe (MAN-01-00505-1.8, 2024-10) (MAN-01-00505-1.8) , p. 8 official manufacturer document quote verified
Wait five minutes before opening the cover