Alarm 2110Power Control Abnormal at Grid Connection Point

Name in the manufacturer's documentation (fault list): Power Control Abnormal at Grid Connection Point[1]

In plain words (editorial)

Power control at the grid connection point is abnormal – meter communication failed or the current at the grid connection point exceeded the threshold, so the inverter stopped grid connection. The manual notes that at most 3 manual startup commands can be sent within 30 days.

When to call a service technician: Have your installer check the meter cable; if the fault persists, contact Huawei technical support.

✎ editorial – written from the cited sources, not a manufacturer statement. Status: draft.

The Polish page has more detail (plain-language explanation, safe checks, guides): Read in Polish →

Sources

Every statement has a footnote to the document and PDF page. “Quote verified” means the quote was found automatically in the text of that page.

  1. [1] Inverter Alarm Reference (Issue 14, 2026-06-15) (EDOC1100345192 Issue 14) , p. 103 official manufacturer document quote verified 2110 Power Control Abnormal at Grid Connection Point
  2. [2] Inverter Alarm Reference (Issue 14, 2026-06-15) (EDOC1100345192 Issue 14) , p. 103 official manufacturer document quote verified the meter communication is abnormal.
  3. [3] Inverter Alarm Reference (Issue 14, 2026-06-15) (EDOC1100345192 Issue 14) , p. 103 official manufacturer document quote verified the current at the grid connection point exceeds the specified threshold.
  4. [4] Inverter Alarm Reference (Issue 14, 2026-06-15) (EDOC1100345192 Issue 14) , p. 103 official manufacturer document quote verified check whether the meter cable is properly connected.
  5. [5] Inverter Alarm Reference (Issue 14, 2026-06-15) (EDOC1100345192 Issue 14) , p. 103 official manufacturer document quote verified manually send a startup command. be noted that a maximum of 3 manual startup commands can be sent within 30 days.
  6. [6] Inverter Alarm Reference (Issue 14, 2026-06-15) (EDOC1100345192 Issue 14) , p. 103 official manufacturer document quote verified if the fault persists, contact your vendor or technical support.
  7. [7] Inverter Alarm Reference (Issue 14, 2026-06-15) (EDOC1100345192 Issue 14) , p. 103 official manufacturer document quote verified when the alarm is generated, the inverter sends a command to shut down and stop grid connection.